Extruded asphalt kerb was successfully introduced along the verge of the new M7 / M8 Portlaoise to Castletown and Cullahill Motorway. Originally the project design provided for insitu concrete kerbs following IrelandÃs traditional practice. However, the schemes Contracts Manager had previously worked in the United Kingdom where extruded asphalt kerb is by a way the […]
In the summer of 2008 Dean & Dyball along with Flint & Neill Partnership were given the task of the refurbishment of the Clifton Suspension Bridge by the Bridge Trust. Upon inspection of the bridge it was found that the original wooden platform beneath the carriageway had deteriorated due to water ingress, and the drainage […]