M1 Junction 28 to 31 – CSB Replacement due to Concrete Contamination

In 2014, Extrudakerb constructed 30km of Concrete Step Barrier along the M1 between junctions 28 and 31. In May 2015, the Principle Contractor, Costain, commenced removal and replacement operations to some of the barrier due to the fact that a contaminate was contained within the concrete. This contaminate issue only became apparent approximately 12 weeks […]